Alpha acted as Construction Manager and designated
General Contractor for the completion of 3 Stadia (out
of 5 in Trinidad & Tobago) for the hosting of the FIFA
Under 17 Women’s World Cup Final.
The works were to be completed in two (2) weeks in
order to host the World Cup games at these venues. Alpha’s hands on approach and ability to manage the
critical path.
The scope of works included:
• Managing over twenty (20) sub‐contractors and
other specialty works including the Stadium
Lighting and Standby Power.
• Liaising directly with various stakeholders
including the Local Organizing Committee (LOC),
FIFA and SPORTT to keep the project on track and
within budget.
• Completing all the necessary refurbishment
works to meet FIFA standards and operating the
Stadiums for the hosting of the games.
SPORTT
ATO BOLDON STADIUM, MANNIE RANJOHN STADIUM & HASLEY CRAWFORD STADIUM
AUGUST 2010 - NOVEMBER 2010